Construction Update (9/11/2015)

Posted: Friday, September 11

Expect nighttime construction work for sign replacement, structure installation and paving. ODOT is partnering with law enforcement for extra presence in the construction zone.

FULL CLOSURE: I-5 SB between Fremont Bridge and Marquam Bridge

  • Expect ramp and lane closures
  • Two weekends:
    • Friday, September 11 and Saturday, September 12
    • Friday, September 18
  • Work will occur between 10 p.m. - noon the following day
  • Traffic detoured to southbound I-405
  • The following Southbound ramps will be closed Friday, September 11 and Saturday, September 12 nights:
    • N Greeley Avenue to SB I-5 closed from 9 p.m. to noon both nights
    • NB I-405 to SB I-5 closed from 9 p.m. - 8 a.m. both nights
    • Westbound I-84 to SB I-5 closed Friday from 10 p.m. - 7 a.m. AND on Saturday from 10 p.m. - 8 a.m.
    • The Moda Center to SB I-5 closed Friday from 11 p.m. - noon AND Saturday from 10 p.m. to noon

I-5 SB between NE Broadway and the Marquam Bridge

  • Ramp closures
  • Monday, September 14 and Friday, September 18
  • Work will occur between 8 p.m. - 6 a.m.

Tentative: I-5 NB between Marquam Bridge and I-84

  • Closure on Thursday, September 17
  • Full closure will start at 10 p.m. – 5 p.m.
  • I-5 travelers will be detoured via I-405
  • Eastbound I-84 travelers will take I-5 S to I-84 eastbound
  • The Morrison Bridge to I-5 NB on-ramps will remain open
  • These ramps will be closed starting at 9 p.m. and will reopen by 5 a.m. the next morning:
    • Southbound I-405 to northbound I-5
    • SW Macadam to northbound I-5
    • SW Broadway to southbound I-405 – open with limited access
    • SW 5th Avenue to southbound I-405
    • SW Montgomery to southbound I-405 – open with limited access

I-5 NB near Convention Center to N Lombard

  • Lane and ramps closures
  • Monday, September 14 through Thursday, September 17
  • Work will occur between 8 p.m. - 6 a.m.

I-5 BOTH DIRECTIONS between Marquam Bridge and Capitol Highway

  • Ramp and lane closures
  • Monday, September 14 to Saturday, September 19
  • Work will occur between 8 p.m. - 6:30 a.m.
  • Expect on- and off-ramp closures throughout the project area
Related Work: Maintenance Crews on I-5
  • Potential lane and shoulder impacts

Entire Project Area

Shoulder closures for temporary sign and detour installation

For detour and project information: visit www.i5PavingandSigns.org. Or call the project hotline (503) 731-4663 or night construction hotline (503) 646-0231.

Related Information


News

Construction Update (09/30/2016)

Paving and sign work on Interstate 5 from SW Capitol Highway to N Lombard Street included replacing…

Construction Update (09/23/2016)

Paving and sign work on Interstate 5 from SW Capitol Highway to N Lombard Street included replacing…

Construction Update (09/16/2016)

Paving and sign work on Interstate 5 from SW Capitol Highway to N Lombard Street included replacing…


Want to see current road conditions on I-5?


Share