Construction Update (5/6/2015)

Posted: Thursday, May 7

The following activity will be occurring on I-5 over this week.  Work will be between 8 p.m. and 6 a.m., unless noted otherwise.

This week:

  • I-5 SB, just south of the I-84 to I-5 on-ramp (MP 301): Drilling will require a right lane and shoulder closure on I-5 and right lane on the I-84 on-ramp between 10 p.m. and 6 a.m. The I-84 on-ramp will remain open.  
  • I-5 NB, between the Rose Quarter and North Lombard (between MP 302 and 305):  Sign surveying will require single and double lane closures.
  • I-5 SB, between Broadway and North Lombard St. (between MP 305 and 302): Sign surveying will require single and double lane closures.
  • Expect continued daytime shoulder closures for site work on I-5 northbound and southbound throughout the project area for temporary sign and detour installation.

Week of 5/11:

  • I-5 NB, between the west end of the Marquam Bridge and North Lombard (between MP 300 and 305):  Preparation for new sign structures will require single lane closures.  Expect two (2) nights of single lane closures on NB Marquam Bridge near MP 300 (one night with left lane closed; one night with the right lane closed.)  This will be for reconnaissance and temporary platform installation.
  • I-5 SB between North Lombard St. and the east end of the Marquam Bridge (between MP 305 and 300):  Preparation for new sign structures will require shoulder and single right lane closures.
  • Marquam Bridge: Expect single and double lane closure on Friday, 5/15 and Saturday, 5/16 between 8 p.m.  and 8 a.m. for survey work
  • I-5 SB Hood St. Ramp: Expect closures between 9 p.m. and 9 a.m on Friday, 5/15 and Saturday, 5/16.
  • I-5 NB Macadam Ramp: Expect closures between 9 p.m. and 9 a.m. on Friday, 5/15 and Saturday, 5/16.
  • Expect continued daytime shoulder closures for site work on I-5 northbound and southbound throughout the project area for temporary sign and detour installation.

 

These dates are subject to change.

Want to see real-time road conditions on I-5? Visit ODOT TripCheck.com

Related Information


News

Construction Update (09/30/2016)

Paving and sign work on Interstate 5 from SW Capitol Highway to N Lombard Street included replacing…

Construction Update (09/23/2016)

Paving and sign work on Interstate 5 from SW Capitol Highway to N Lombard Street included replacing…

Construction Update (09/16/2016)

Paving and sign work on Interstate 5 from SW Capitol Highway to N Lombard Street included replacing…


Want to see current road conditions on I-5?


Share