Construction Update (4/9/2015)

Posted: Thursday, April 9

The following activity will be occurring on I-5 over the next several weeks.  All activity will be nightwork, from 9 p.m. to 6 a.m.  

This week:

  • Construction work will continue at I-5 SB at MP 301. This work will require a right lane closure just north of Exit 301/ I-84 EB, however the ramp will remain open.  It will also require a closure of the Wheeler I-5 SB on-ramp and nearby right lane and shoulder closures.
  • Drilling will occur at I-5 NB at MP 305, north of Rosa Parks.  This work will require a closure of the I-5 NB on-ramp from Rosa Parks and nearby right lane and shoulder closures
  • Construction will occur at I-5 SB at MP 303. This work will require a closure of the I-5 SB on-ramp from Going St and nearby ramp and shoulder closures.
  • Construction work will occur at I-5 SB at MP 302. This work will require a right lane closure on I-5, just south of the I-5 / I-405 interchange.  It will also require a closure of the on-ramp to I-5 SB from Greeley  and nearby right lane and shoulder closures. Traffic will be detoured to Going St.  Exit 302A (Broadway/Weidler) to remain open.

Starting the week of 4/13:

  • Construction and drilling will continue to occur at I-5 SB at MP 303 (just south of Going Street).  This work will require a closure of the Going St. to I-5 southbound on-ramp and shoulder.
  • Construction will occur at I-5 SB at MP 302 (just south of I-5 to I-405 on-ramp). This work will require a closure of the right lane and shoulder.  Note: work hours will be between 10 p.m. to 6 a.m.)
  • Additional drilling work will occur at I-5 SB at MP 302 (just south of I-5 / I-405 interchange). This work will require a closure of the Greeley to I-5 southbound on-ramp, right lane and shoulder. Exit 302A (Broadway/Weidler) to remain open.
  • Construction will occur at I-5 SB at MP 301 (just south of the I-84 to I-5 on-ramp). This will require a closure of the right lane and shoulder, and right lane of I-84 on-ramp between 10 p.m. – 6 a.m. however, the I-84  on-ramp to remain open. 

These dates are subject to change.

Want to see real-time road conditions on I-5? Visit ODOT TripCheck.com

Related Information


News

Construction Update (09/30/2016)

Paving and sign work on Interstate 5 from SW Capitol Highway to N Lombard Street included replacing…

Construction Update (09/23/2016)

Paving and sign work on Interstate 5 from SW Capitol Highway to N Lombard Street included replacing…

Construction Update (09/16/2016)

Paving and sign work on Interstate 5 from SW Capitol Highway to N Lombard Street included replacing…


Want to see current road conditions on I-5?


Share