Construction Update (3/17/2015)

Posted: Tuesday, March 17

The following activity will be occurring on I-5 over the next several weeks.  All activity will be nightwork.

This week:

  • Nightwork (8 pm-5:30 am) to prepare for new signs will require shoulder and single lane closures.
  • Drilling will occur at I-5 SB at MP 305.23 (just south of Lombard).  This site work will require closures of the Lombard to I-5 SB on-ramp, the right shoulder and right lane between 8 pm – 5:30 am.

Starting the week of March 23:

  • Drilling will occur at I-5 NB at MP 301.13 (just north of the I-84 ramp). This work will require a single right lane closure on I-5 NB and a single left lane closure on the I-84 on-ramp between 10 pm – 5 am. The I-84 on-ramp (Exit 300) will remain open.
  • Drilling will occur at I-5 NB, MP 305.12 (just north of Rosa Parks on-ramp). Site work will require ramp, lane and shoulder closures between 8 pm – 5:30 am.
  • Drilling will occur at I-5 NB, MP 302.7 (just north of Broadway on-ramp). Site work will require ramp, lane and shoulder closures between 8 pm – 5:30 am.

Want to see real-time road conditions on I-5? Visit ODOT TripCheck.com

Related Information


News

Construction Update (09/30/2016)

Paving and sign work on Interstate 5 from SW Capitol Highway to N Lombard Street included replacing…

Construction Update (09/23/2016)

Paving and sign work on Interstate 5 from SW Capitol Highway to N Lombard Street included replacing…

Construction Update (09/16/2016)

Paving and sign work on Interstate 5 from SW Capitol Highway to N Lombard Street included replacing…


Want to see current road conditions on I-5?


Share