Construction Update (12/11/2015)

Posted: Friday, December 11

ODOT is partnering with law enforcement for extra presence in the construction zone.

FULL CLOSURE: 1-5 SB Going Street on-ramp

  • FULL CLOSURE of Going Street on-ramp
  • Double lane and shoulder closures (between N Lombard and Marquam Bridge)
  • Monday, Dec. 14 to Friday, Dec. 18
  • Closure will occur between 8 p.m. to 6 a.m., full closure 10 p.m. to 6 a.m.

FULL CLOSURE: I-5 NB (Fremont Bridge) ramp to I-405

  • FULL Closure of I-5 NB (Fremont Bridge) ramp to I-405
  • Friday, Dec. 11
  • Closure will occur between 10 p.m. and 6 a.m.

I-405 BOTH DIRECTIONS: I-405 Fremont Bridge

  • Single lane and shoulder closures in both directions on I-405 Fremont Bridge
  • Monday, Dec. 14 to Saturday, Dec. 19
  • Closure will occur between 8 p.m. to 6 a.m.

Project hotline: (503) 731-4663

Night time construction hotline: (503) 646-0231

Project FAQ’s: i5pavingandsigns.org/page/faqs

Related Information


News

Construction Update (09/30/2016)

Paving and sign work on Interstate 5 from SW Capitol Highway to N Lombard Street included replacing…

Construction Update (09/23/2016)

Paving and sign work on Interstate 5 from SW Capitol Highway to N Lombard Street included replacing…

Construction Update (09/16/2016)

Paving and sign work on Interstate 5 from SW Capitol Highway to N Lombard Street included replacing…


Want to see current road conditions on I-5?


Share